As of today there are 2000 of the roughly 14000 hotel rooms open for business. Many more coming on line during the second half of October and I believe all by Christmas at the latest.
Latest update:
October 15 - 5000 hotel rooms open
November 15 - 7000 rooms open
December 15 - 10000 rooms open
Most of San Lucas is cleaned up and open for business including Squid Roe, Giggling Marlin, Nick San, Baja Cantina, Solomon's, Capatin Tony's, Cab Cantina... you get the picture downtown has a relatively normal feel to it already, well except for Paul and Bill's new beards. Wink
Walmart, Soriana (large supermarket chain), Almost every bank, All but 1 gas station - back open
Golf
October 1 openings-Puerto Los Cabos
-Club Campestre San José
-Cabo Real
-Cabo del Sol - Ocean (back nine) - 9 holes $75 / All Day $125
October 4 openings-Cabo San Lucas CC
October 6 openingsQuivira
Other
Palmilla - may be out of commission through November but may open sooner. Hit hard in maintenance office and electronics/irrigation issues must be addressed though the golf course is fine.
Querencia - some minor erosion issues, not sure they have set a date but it won't be an extended closure.
Diamante Dunes - Course is fine, just uncovering sand that migrated west
Paul can speak to specific dates and such.
El Dorado - No reports but assumption is they are fine apart from minor erosion and fallen trees/cacti
Mayan Golf Course (9) - Mid to late November opening
Cabo del Sol Desert - Opening sometime mid-November. NO issues just dedicating staff to clean up for this period as there will be little need for a 36 hole operation until we host the Taylor Made Invitational beginning Nov 17.
Ocean Course Front Nine - Likely November 1. Hole 7 was hardest hit in the region and while it should be put back together as of today it will still need some TLC so we can open in excellent condition.
Chileno Bay - No reports.