moving dirt is generally accomplished and quantified by three methods [ and this varies ] ;
'push' dirt ,generally small cuts and fills made during rough and final shaping,usually with a dozer.
'panned' dirt, cuts made with pans and scrapers and moved in short and long hauls ,generally ,but not always ,on site.
'top loaded' dirt,excavated by trackhoe or other method,and loaded on dump truck or pan for transport.
....costs ,from low to high, generally follows the above ,with calculations being based on cubic yards moved [cuts].
....most projects try to balance thier cuts and fills on site,to aviod the higher costs associated with importing materials.