This course is closed for renovation until May 2007:
Here is the invitation to bid:
INVITATION TO BID (ITB) 21-06/07
FOR NORMANDY SHORES GOLF COURSE IMPROVEMENTS
Sealed bids will be received by the City of Miami Beach Procurement Director, 3rd Floor, 1700 Convention Center Drive, Miami Beach, Florida 33139, until 3:00 p.m. on the 30th day of January 2007 for: NORMANDY SHORES GOLF COURSE IMPROVEMENTS
Scope of Work:
Work to be performed under this Contract shall consist of furnishing and installing all tools, equipment, materials, supplies, and manufactured articles and furnishing all labor, transportation, and services, including fuel, power, water and essential communications, and performing all work, or other operations require for fulfillment of the contract in strict accordance with the Contract Documents.
The Scope of the work is to provide all materials, labor, equipment, supervision, mobilization, overhead & profit required to provide but not limited to the following:
1. Eradication of existing turf using applications of Round-up as defined for areas shown on the turf eradication plan.
2. Removal of invasive tree and shrub vegetation identified on the tree removal plan.
3. Removal of all existing golf cart path.
4. Renovation of eighteen tee complexes and practice range tee.
5. Renovation of nineteen greens including practice putting green.
6. Renovation and/or construction on bunkers/sandtraps.
7. Installation of new asphalt cart path in eight and twelve foot widths as identified in the construction drawings.
8. Installation of golf feature (e.g. bunker and greens) drainage systems.
9. Installation of limited drainage system including basins, piping, and outfall control structures for moderate surface flow.
10. Sprigging of specified Paspalum grass for all areas where the existing turf was eradicated.
11. Installation of new pump station including connections to the public water supply with associated control fittings, brackish water intake, and fertigation system.
12. Construction of new pump house structure.
13. Installation of new irrigation system including connection to the new pump station, new piping, new irrigation heads, control system, and control lines.
14. Construct a drainage pump station with three low pressure electrical pumps to convey the on-site runoff to three drainage wells.
15. Construct three pressurized drainage wells.
16. Enlarge two lake areas to provide more storage.
17. Construct a berm surrounding the golf course to contain on-site stormwater. The berm elevation will be set at the peak stage of a 25-year, 72-hour storm event while discharge to groundwater wells at the approximate pre-condition 5-year, 24-hour peak discharge rate.
18. Interconnect on site lakes with HDPE pipes.
19. Build two control structures on the lakes to provide require water quality treatment volume within the lake system.
Estimated Budget: $6,100,000
Minimum Requirements: Contractor must be a Certified Member of the Golf Course Builders Association of America. They must establish that they have been in the golf course construction business for at least five years under their current name, and have completed construction of 18 holes of golf course, or the equivalent, per year for each of the past five years under the direction of an architect. Provide references from individuals in five of the following seven categories: course owner/developer, golf course architect, engineer, irrigation designer, golf course superintendent, municipality, and/or certified golf course builder.
Added on Jan 19, 2007:
Addendum #1
Attached Addendum document changes the bid due date to February 13, 2007 at 3:00 PM
Also, the Minimum requirement for the bid has been Amended. The amended language is as follows:
Minimum Requirements: Golf Course Contractor must be a Certified Member or Associate Member of the Golf Course Builders Association of America, or a Golf Contractor must establish that they have been in the golf course construction business for at least five years and have completed construction of an 18 hole golf course construction project in the past 3 years.
www.rfpdepot.com/DPX?ac=view&auc=94789