joe,
we have completed bunker work on 14 holes so far. this includes adding many new bunkers, eliminating some bunkers, and reshaping some bunkers. we have also added some new tees on those holes, but there are still some tees on jim's plan that still need to be built. we have also been gradually removing trees necessary for the plan.
holes 8 thru 17, 1,2,4,5 have all new bunker schemes.
we have been working with jim primarily around his schedule, he lives close by and when his schedule permits he comes out and does some work for us. we plan to continue upgrades to the course during the next fall winter season.
i would say that we have completed about 75% of the plan with the remainder to be done in the next year or so, all work is mainly done in the off seasons while the course remains open for play. but we plan to continue our relationship with Jim Wagner even after we complete this stage. we will continue to seek his advise and implement improvements when funds become available